News
-
December 12, 2023December 2023: Stage 3 of Boróka Park is completed
-
August 24, 2023External thermal insulation and coloring in progress
-
December 10, 2022The facade windows have been installed.
-
October 26, 2022The masonry works are coming to an end.
-
September 20, 2022The support structure is ready
-
May 20, 2022The structure is being built.
-
November 16, 2021Boróka Park Phase 3 launches
-
November 12, 2020Boróka Park Phase 2 completed
-
November 16, 2020Finishing works are underway in flats and communal areas
-
October 12, 2020The balcony railings are in place
-
September 21, 2020Western façade completed
-
August 21, 2020The cold cladding of the apartments is in progress
-
July 24, 2020Facade works to be completed soon
-
June 19, 2020The building complex is getting more and more colorful
-
May 25, 2020The interior works are progressing very well
-
March 4, 2020Plastering of internal walls and thermal insulation of the floor has started
-
January 23, 2020Facade insulation, mechanical and electrical installation works in progress
-
December 13, 2019The installation of facade windows and roof insulation is in progress
-
November 18, 2019Construction is underway
-
October 28, 2019The construction of the structure is completed
-
September 12, 2019Masonry work has already started
-
August 15, 2019Formwork of the 3rd floor slab of the building
-
July 15, 20191-2 floor slab structures are being constructed
-
June 30, 2019The slab structure of the reception level of building A is completed.
-
May 15, 2019The sole beams are getting ready
-
January 7, 2019Landscaping works for phase 2, which has a valid construction permit, are underway
-
October 25, 2018Our website is ready
-
September 20, 2018Boróka Park II. Preparation stage
-
July 18, 2018Boróka Park II. Planning phase